Testimonials
Port of Galveston Cruise Terminal
- Type of construction: Renovation/Remodel
- Size of project: 35,000 sqft
- Duration of project: 2 years
- Percentage of labor that is self-performed: 100%
Project Summary
Holes Incorporated was contracted by Texas Gulf Construction to support the Port of Galveston’s Terminal 25 improvement project in preparation for the arrival of Carnival Jubilee. The team cut, drilled, wire sawed, slab sawed, and removed approximately 1.3 million pounds of concrete pier decking and pilings while protecting the integrity of the remaining structure. Work was completed over open water in an active cruise and cargo port, requiring careful safety planning, environmental protection, security coordination, and precise crane-assisted removal methods. Despite challenging site conditions and a tight schedule, Holes completed the project on time and helped strengthen the terminal for expanded cruise operations.
From the Client
Kirby Interchange
- Type of construction: Concrete Removal
- Size of project: 30’ x 1,025’
- Duration of project: 6 Months
- Percentage of labor that is self-performed: 100%
Project Summary
Holes completed a turnkey civil and site improvement project for Brewer Construction-Transwestern D1, delivering ADA-compliant sidewalks, ramps, stairs, interior slab repairs, plumbing trench work, canopy footings, generator foundations, and masonry upgrades. The team successfully managed tight site conditions, active building operations, limited ventilation, inclement weather, and coordination with multiple trades while maintaining safety and schedule requirements. Precision concrete cutting, demolition, drilling, pour-back work, and careful debris management allowed Holes to complete complex interior and exterior scopes efficiently and to specification. The project was completed on time and within budget, strengthened the customer relationship, and led to additional awarded work.
From the Client
“The Holes Incorporated team consistently guided us through numerous challenges, enabling the successful completion of multiple projects at the Kirby Interchange. Their expertise was invaluable in overcoming obstacles such as working within occupied spaces, constructing temporary access points for active areas, managing unstable soild, and drilling piers in extremely confined locations. Our longstanding relationship with Holes Incorporated is build on their unmatched precision, commitment to project excellence, efficiency, and safety.”
Tranquility Park Beautification Project
- Type of construction: Wall Removal
- Size of project: 810 Linear Feet
- Duration of project: 3 weeks
- Percentage of labor that is self-performed: 100%
Project Summary
From the Client
Dow Poly 6 Project
- Type of construction: Demolition
- Size of project: Wire Saw 10-2’6”x2’6” Pedestal & 17- 2’x2’ beams
- Duration of project: 2 weeks
- Percentage of labor that is self-performed: 100%
Project Summary
Holes Incorporated was hired to provide specialty demolition support for the Dow Poly 6 project, completing precision wire sawing on structural concrete elements within a two-week project window. The contracted scope included wire sawing ten 2’6” x 2’6” pedestals, cutting three feet of slab vertically across the aligned pedestals, and making two horizontal cuts on each of the seventeen 2’ x 2’ beams. With 100% of the work self-performed, Holes delivered the technical cutting expertise required for accurate removals while maintaining responsive communication and dependable execution.
From the Client
“We appreciate the great work the Holes Team performed at our Dow Poly 6 Project. Look forward to future projects that we need to utilize your specialty work.”